| Project
Status
DRI
PLANT
For the overall DRI Plant, the engineering
portion of the Core Plant is complete and
98 % of the structure fabrication, erection
and equipment purchases have been finalized
with approximately 70% of equipment purchased
and delivered at site. Fabrication and construction
is proceeding in earnest with the Core Plant,
Water Treatment, Material Handling and associate
infrastructure which have emerged on the ground
and are in view.
DRI FURNACE
All piling and foundation work has been completed
and second phase of the structural erection
is in progress. As the fabricated steel is
arriving from the fabricator (HMC in Taxila)
it is being promptly put in place and bolted
to the previous members.
REFORMER
All foundations are complete. Fabrication
and the erection of the Reformer is in full
swing.
The Lower Feed Gas Ducts and the main support
structural steel frames have been installed,
while the floor and roof panel installation
is in progress.
Reformer area piping has been contracted out
(ICC).
HEAT RECOVERY
The fabrication and erection of the boxes
and the stack of the Heat Recovery are near
completion and the refractory work is almost
complete.
WATER TREATMENT
Foundation and the concrete bottom of the
Clarifier have been completed. The Steel Shell
is now in fabrication in the Central Maintenance
Department (CMD) of TSML. Order has been placed
for Cooling Tower, whereas construction of
its foundation and Reservoir is under process.
Settling Ponds have been completed.
PIPE RACKS
All pipe rack foundations are in progress
and the fabrication of the structural steel
has been contracted out (ABS).
FLOOR PIPING
Furnace and water complex area pipings have
been contracted out (ABS).
BUILDINGS
Control Building: Construction is in progress.
The ground floor and rough building structure
have been completed.
Analyzer building: Construction of the rough
building and roof has been completed.
ELECTRIC
POWER PLANT
Layout / demarcation of the 35MW Combined
Cycle Power Plant has been completed. Excavation
for Gas Turbines has been started.
REVERSE OSMOSIS
(RO) PLANT (FOR CONSTRUCTION PURPOSE)
The 500 CUM/day capacity RO plant for the
general site services was completed by mid-2007
and has been providing potable water for the
construction activities. The water is obtained
from the wells drilled for this purpose.
NG METERING STATION
The natural gas supply line has been completed
by SSGC but the Metering Station by them is
to be installed. However, purchase order of
Metering Station for DRI (to be installed
by TSML) has been placed.
CONCRETE BATCH PLANT
The Batch Plant had been completed by mid-2007
and has been fully functional and providing
ready-mixed concrete to the DRI project. With
the only exception of the furnace foundation
where very large amount of concrete was required
to make a continuous pour, the TSM Batch Plant
has provided all concrete for the DRI Project
and for all the general civil works.
TSM FABRICATION
SHOP (CMD)
The CMD Fabrication Shop has been constructed
and outfitted with Machine Shop and fabrication
equipment. There is a current effort to upgrade
the shop with higher production equipment
to increase the quantity of steel fabrication.
As a temporary step a local Pakistani fabricator
has been contracted to utilize the TSM fabrication
facilities and equipment. Fabrication is currently
being done both by TSML and the fabrication subcontractor.
WATER SUPPLY SYSTEM
Survey and design of 18 Km Water Supply Line
have been completed. The job is in the process
of being contracted out.
Design of 36000 CUM potable Water Reservoir
completed. Excavation and construction by
civil contractor has been undertaken.
RO PLANT
(FOR DRI PLANT)
The civil design of the RO plant for the DRI
Plant is now in process and the site has been
cleared and ready for the start of the civil
work.
Treated Water Tanks are under designing by
the consultants.
|